Friday, July 25, 2014

Picture Update

I hope everyone had a great 24th of July holiday.  Here's the picture update for the week.  There's more and more electrical going in as you walk down the hall from the more finished part of the building to the less finished part.  More carpet is continuing to go in and they are starting to prep one section of the hall floors for tile.   They are also working on prepping the road to be paved.   Some of you may have noticed that they have closed off part of 1100 West and they are working on piping the irrigation in preparation for a sidewalk.

 Basketball Hoops in gym

 Hall by the gym

 Classroom

 Playground being installed




 Classroom

 Kindergarten Playground

 Kindergarten Classroom


 Concrete in the front of the school


 Ceiling tiles in the main entry


 There's still lots of boxes and stuff in the gym, waiting to be installed.

 Some bathrooms are getting sinks and mirrors

Prep work for tile in the hallway